TextAssessing Gage Stability
George Schuetz, Mahr Federal Inc.
When multiple part measurements show unacceptable variation, it is essential to understand whether it is the manufacturing process, or the measuring process that is at fault. If inaccurate measurements are relied upon, one may make adjustments to a manufacturing process that is in reality accurate and under control. George Schuetz, Mahr Federal Inc.
Gage stability implies different things in different contexts. If taken literally, it may refer to whether there is something loose on the gage, or some other gage problem occurs randomly, to cause two identical trials to produce different results. When plotted on a histogram, this type of instability shows up as a distortion of the expected bell-curve shape-perhaps in the form of dual modes (i.e., high points) with a dip in-between, or in a mode that is skewed toward one end of the tolerance range or the other.
Other types of stability are best assessed and visualized through the use of control charts, in which measurements of several small lots, each represented by a histogram, are compared over a period of time. A single, certified master or other qualified part should be used for the entire series of repeated trials. This serves to eliminate part-to-part error as a variable, so remaining variation will likely be low. Nevertheless, testing may show that variation between lots becomes significant enough over an extended period so as to constitute a measurement problem.
"Statistical stability" refers to the consistency of the measuring system's performance from lot to lot. If a gage is statistically stable, each lot or histogram will be nearly identical in shape and range (R), and the average value (X-bar) of subsequent lots will be close to one another. If it is statistically unstable, the histograms will vary in terms of their X-bar or R values, or both.
Figure 1 shows statistical instability of both sorts. The histograms vary considerably in their ranges and shapes, while the mean dimensions are clearly irregular from lot to lot. "Long-term" and "short-term" stability are confusing, because both require a long-term effort to assess. Both describe trends in the X-bar or R values across multiple lots. If we were to draw a line connecting the X-bar value of each histogram in Figure 1, we would observe no clear trend. Thus, we cannot make a meaningful assessment of either long- or short-term stability.
In Figure 2, the R values are nearly identical, and the X-bar values are grouped much more closely, so the gage is statistically stable. A line connecting the X-bar values would show a clear trend along the nominal value, so we have good long-term stability. This chart shows realistically how the performance of a good, stable gage looks.
Figures 3 and 4 both show good statistical stability. But in Figure 3, there is a short-term stability problem, with a bias in the plus direction. After a few sets of trials, however, the measurements become stable and remain so over the long term. The problem may be due to a warm-up condition in the gage itself. Or it might be the result of contamination that has settled on the gage over night. The X-bar value shifts as the contaminant is dispersed, due to mechanical interaction between the gage and the samples being measured. After a few dozen trials, all the contaminant is dispersed and the measurements become stable. Figure 4 illustrates the opposite situation. The gage is stable on startup and over the short term, but over the longer term it becomes unstable as the X-bar values begin to drift upward. This might be the result of external thermal influences. If performance were be charted over a longer period, the X-bar values might drift back toward nominal again; this might indicate the gage is responding as the plant warms up in the morning, then cools down toward evening.
It is important to check gages for stability, in order to avoid making inappropriate adjustments to the manufacturing process. In some cases, solving the problem may be simple as establishing a more frequent schedule for re-mastering the gage. In others, it could require a reevaluation of the entire gaging process.